Dholera Bhavnagar expressway: where the extension stands in November 2026
Updated 11 November 2026. Compiled by the Dholera SIR News desk from the sources listed at the end of this page.
The Ahmedabad-Dholera expressway ends near Dholera and has not yet been extended to Bhavnagar. On 10 July 2026 Union Minister Nitin Gadkari said extension work would begin within three months, which ended around 10 October 2026. We found no report of a start, length, cost or contractor as of 13 November 2026.
The extension, dated, with how solid each item is
| Date | What was reported | Source | How solid |
|---|---|---|---|
| November 2025 | Review meeting on the expressway, later cited by the minister as the point from which progress was measured | DeshGujarat, 10 July 2026 | Reported |
| 9 December 2025 | Motorists use the unopened expressway for the Ahmedabad to Bhavnagar trip, cutting it to about 2.5 hours | DeshGujarat, 9 December 2025 | Reported |
| 27 February 2026 | Expressway open to the public for testing | PIB release 2233516 | Official |
| 31 March 2026 | Expressway inaugurated by the Prime Minister | PIB New India Samachar, 16-30 April 2026 | Reported |
| 10 July 2026 | Gadkari says work to extend it to Bhavnagar starts within three months | DeshGujarat | Reported, no document |
| About 10 October 2026 | Three-month window ends; no start reported in our record | Our search to 13 November 2026 | Not found |
| 13 November 2026 | Length, cost, contractor and alignment of the extension not stated anywhere we hold | Our record | Unknown |
Download this table (CSV). Last checked 11 November 2026. Free to quote with a link to this page.
What the minister said
DeshGujarat reported on 10 July 2026 that Nitin Gadkari, Union Minister for Road Transport and Highways, told a review meeting in Gandhinagar that work on extending the Ahmedabad-Dholera expressway onward to Bhavnagar would begin within the next three months. The meeting was with Chief Minister Bhupendra Patel and senior state officials. He also asked the state to send proposals for central road fund financing, which suggests the project was at the funding and planning stage, not the construction stage. Our wire entry Gadkari said work on extending the Dholera expressway to Bhavnagar starts within three months keeps the original report.
Has work started?
Three months from 10 July 2026 is about 10 October 2026. By 13 November 2026 we found no report that construction, a tender, a land acquisition notice or a contract award had followed. A search for the topic returned the July statement and later copies of it, and no newer official release. This is a negative finding and a limit of our record: a start could exist in a local notice we have not seen. A start of work would normally appear in an NHAI tender notice or a Ministry of Road Transport release, and neither has been found.
What is known about the length, cost and route
Nothing is stated. The July report gives no length, no cost and no contract. Wikipedia lists the expressway's southern end at Adhelai in Bhavnagar district, which is where an extension would pick up, but that is a reference work and not a project document. Press versions say the Ahmedabad to Bhavnagar trip would fall from nearly four hours to around two once the extension is built. That is a projection, and no figure of this kind has been tied to a design or a date.
What the Dholera expressway itself shows about timing
DICDL's own annual reports are the best guide to how targets behave here. The 2023-24 report put the Ahmedabad-Dholera expressway at 51 per cent progress with completion planned by January 2025. The 2024-25 report put it at 95 per cent with completion slated for the end of 2025. It then opened to the public for testing on 27 February 2026 and was inaugurated on 31 March 2026. The deadlines that moved entry sets out both. A three-month start target for the extension deserves the same patience.
A court ruling on land for the existing expressway
One ruling is worth knowing before any extension is planned. Swarajya reported that on 29 April 2026 the Gujarat High Court cancelled the acquisition of additional land for the Ahmedabad-Dholera expressway in Bholad village, Dholka taluka: two plots of 21,314 square metres. NHAI was directed to recover a Rs 13.91 crore deposit, and the court ordered a fresh inquiry into the officers involved. The report states no effect on the opening of the road, and we have not seen the judgment itself, so treat this as reported. It shows that land for a new stretch can be contested in court, which is a reason to watch for a land acquisition notice before expecting construction.
The tolls on this corridor
DeshGujarat reported in May 2025 that a toll rate notification had been issued covering a 23 km stretch of NE-8 and a 30 km stretch of NH-751 on the Dholera to Bhavnagar route. We found no published toll figure for the Ahmedabad-Dholera expressway for cars as of 11 November 2026 and print none. Amended fee rules in force from 15 February 2026 charge lower rates on partially open expressways, so any toll quoted on a blog should be checked against a notification.
Why an extension matters for Dholera
The first expressway links Dholera to Ahmedabad. An extension would link it to the Bhavnagar coast and turn a road that ends near the SIR into part of a longer corridor. That changes the logic for freight and for people travelling between the two cities, and it is the reason the July statement drew attention. It does not change what is on the ground today, which is an expressway that stops where it stops.
What would confirm a start
Three documents would settle it: an NHAI or Ministry notice inviting bids for the extension, a notice acquiring land along the route, or an award to a named contractor. Our connectivity topic page will carry any of them, dated and labelled.
What this page cannot tell you
This page records reports and a negative search result to 13 November 2026. It cannot tell you the length, cost or alignment of an extension, or whether work has begun in a place we have not seen reported.
Questions people ask
Is the Dholera Bhavnagar expressway under construction?
No report found as of 13 November 2026 says so. On 10 July 2026 Union Minister Nitin Gadkari said work on extending the expressway to Bhavnagar would begin within three months, and no start, tender or contract has been reported since.
What did Gadkari say about the Bhavnagar extension?
DeshGujarat reported on 10 July 2026 that he told a review meeting in Gandhinagar that extension work would start within three months and asked Gujarat for proposals for central road fund financing.
How long is the Dholera to Bhavnagar extension?
Not stated. The July 2026 report gives no length, cost or contract for the extension. The existing Ahmedabad-Dholera expressway is 109.019 km according to the road ministry release.
When will the Ahmedabad Bhavnagar journey be faster?
Only after an extension is built. Press reports say it could fall to about two hours from nearly four, but no completion date has been given.
Is the Ahmedabad Dholera expressway open?
Yes. It opened to the public for testing on 27 February 2026 per a PIB release and was reported inaugurated on 31 March 2026. We found no published toll figure for cars.
Where does the Dholera expressway end now?
Near Dholera SIR. A reference listing places the southern end at Adhelai in Bhavnagar district, which is where an extension would pick up, but no project document confirms the alignment.
Read next
- Dholera metro rail: no metro approved, a 134 km rail line is
- Gadkari on the Bhavnagar extension
- Expressway deadlines that moved
- Expressway opens
- Connectivity news
Sources
- DeshGujarat: Gadkari on Dholera expressway extension to Bhavnagar (10 July 2026)
- PIB release 2233516: Ahmedabad-Dholera expressway, Ministry of Road Transport and Highways (27 February 2026)
- DeshGujarat: Ahmedabad-Bhavnagar travel cut to 2.5 hours as motorists use Dholera expressway unofficially (9 December 2025)
- DICDL 9th Annual Report 2024-25, external connectivity (signed 22 August 2025)
- PIB New India Samachar, 16-30 April 2026, page 52: Ahmedabad-Dholera expressway inauguration (April 2026)
- Swarajya: Gujarat High Court cancels Ahmedabad-Dholera expressway land acquisition in Bholad (29 April 2026)