Sarkhej to Dholera semi-high-speed rail tender: what has been reported
Updated 11 November 2026. Compiled by the Dholera SIR News desk from the sources listed at the end of this page.
Western Railway has opened an engineering, procurement and construction (EPC) tender for the 134 km Sarkhej to Dholera semi-high-speed double line, reported at Rs 18,901.68 crore in August 2026. The Cabinet approved the whole project at Rs 20,667 crore on 13 May 2026. No contract award has been reported as of 13 November 2026.
The rail tender in dated steps
| Date | Step | Source | Label |
|---|---|---|---|
| 13 May 2026 | Cabinet approves the 134 km Ahmedabad (Sarkhej) to Dholera semi-high-speed double line at Rs 20,667 crore | ThePrint | Reported by a national outlet |
| 29 May 2026 | Western Railway meets more than 20 firms on the project; EPC tender said to be coming soon | DeshGujarat | Reported |
| Early August 2026 | EPC tender reported open at about Rs 18,901.68 crore; scope includes spur lines to the Lothal heritage complex and the Dholera airport terminal | India Shipping News, 3 August 2026; Raillynews, 6 August 2026 | Reported, exact bid-opening date not found |
| 16 October 2026 | State review notes the line will link Ahmedabad, Dholera SIR, the airport and Lothal | NewKerala wire | Reported |
| 13 November 2026 | No contract award reported | Search of the sources above | Not found |
Download this table (CSV). Last checked 11 November 2026. Free to quote with a link to this page.
What an EPC tender means
EPC stands for engineering, procurement and construction. The winner designs the work, buys the material and builds it, and is paid under one contract. A single package on a 134 km line is large, and the reports describe it as bundling the civil works, the spur lines and the commissioning into one contract. The reports do not say whether several bidders may form a joint venture, so this page does not say so either.
Two numbers that are easy to confuse
The Cabinet approved a project cost of Rs 20,667 crore. The tender is reported at Rs 18,901.68 crore. The first is the approved cost of the whole project. The second is the value of the construction package that has been put out for bids. The reports do not explain the difference, and it should not be assumed to be spent on land or other items.
What the line is meant to connect
According to the 16 October 2026 review reported by NewKerala, the line will link Ahmedabad, Dholera SIR, the airport and Lothal. A separate 23 km line from Bhimnath to a Dholera logistics hub is being developed. These are planned links. None is operating as of the date above.
What happens after a tender opens
- Bidders submit technical and financial bids by the stated deadline.
- The railway evaluates the technical bids and then opens the financial bids of those that qualify.
- The railway issues a letter of acceptance to the selected bidder and signs the contract.
- Construction begins after the contract and the handover of land.
The reports found do not give the deadline or any later step, so no timetable is stated here.
What this page does not say
The record holds no bidder names, no bid amounts, no deadline and no start date for construction. Some reports give a design speed, and they disagree with one another, so a speed is not printed here. This page will be updated if Western Railway or the Ministry of Railways publishes an award or a schedule.
What this page cannot tell you
This page tracks reports on one tender. It cannot name the bidders, say when bids close or say when trains will run.
Questions people ask
What is the Sarkhej to Dholera rail tender worth?
The EPC tender was reported at Rs 18,901.68 crore in August 2026. The Cabinet approved the whole project at Rs 20,667 crore on 13 May 2026. The two figures describe different things: the first is a construction package, the second the project cost.
Who has won the Dholera semi-high-speed rail contract?
No award has been reported as of 13 November 2026. The sources found describe the tender being open and a pre-bid meeting with more than 20 firms in May 2026. They name no bidder and no winner.
How long is the Ahmedabad to Dholera semi-high-speed line?
The approved line is 134 km of double track between Sarkhej in Ahmedabad and Dholera. The tender scope also includes spur lines to the Lothal heritage complex and the Dholera airport terminal.
When will the Dholera rail line be built?
No construction start or completion date is in the record. The tender is open and no award is reported, so any date quoted for the line should be treated as an unconfirmed target.
Which agency is running the tender?
Western Railway, through its Ahmedabad survey and construction organisation, per the reports. The Cabinet approval on 13 May 2026 came from the Union Cabinet.
Read next
- The rail pre-bid meeting
- Semi-high-speed rail approved
- Is there a Dholera metro?
- Connectivity news
- Announcements since August 2026
Sources
- Cabinet approves 134 km semi-high-speed rail line between Ahmedabad and Dholera for Rs 20,667 crore, ThePrint (13 May 2026)
- 20+ firms participate in meeting for Sarkhej to Dholera semi-high-speed rail project, DeshGujarat (29 May 2026)
- Initiation of the semi-high-speed railway tender in India, Raillynews (August 2026)
- Gujarat CM takes stock of projects in Dholera region, NewKerala (16 October 2026)