AAI's operation and maintenance agreement for Dholera airport, explained

Updated 11 November 2026. Compiled by the Dholera SIR News desk from the sources listed at the end of this page.

On about 4 November 2026 the Airports Authority of India signed an operation and management agreement with the Dholera International Airport Company Ltd. The report describes it as an operational partnership between the two. It is not an opening and not a licence. No terms or date were published, and the airport is still expected to be operational by the end of 2026.

What was signed

CAPA, an aviation research outlet, reported on 4 November 2026 that the Airports Authority of India (AAI) and the Dholera International Airport Company Ltd (DIACL) signed an operation and management agreement for the Ahmedabad Dholera airport. Indian Masterminds carried the same report on 3 November 2026. The signatories named in the report were Anami Pandey, a general manager of AAI, and H.M. Chavda, the chief operating officer of DIACL.

The report gave no terms, no start date and no opening date. We have not read the agreement, and the AAI release was not available to us, so this page rests on the two reports and labels the item as reported.

Who the two parties are

The Airports Authority of India is the central government body that runs most of India's civil airports. DIACL is the company that is building Dholera International Airport. It is a joint venture in which AAI holds 51 per cent, the Government of Gujarat 33 per cent and the National Industrial Corridor Development Corporation (NICDC) 16 per cent. Phase 1 is a single 3,200 m Code 4E runway.

The report does not describe the arrangement between the two in more detail.

What an operation and maintenance agreement does

An operation and maintenance agreement names who runs the airport day to day and who keeps its runway, terminal and equipment in working order. It is a step taken before an airport carries passengers, because someone has to be responsible for operations on the day it opens.

It does not itself allow flights. A new airport also needs an aerodrome licence from the Directorate General of Civil Aviation, and airlines need to announce flights. As of 11 November 2026, neither a licence nor an airline schedule has been reported.

Where the airport stands in the record

  1. 4 June 2026: the first trial landing, by an Airports Authority of India aircraft, on the 3,200 m runway. It was a test and not an opening.
  2. July 2026: after a ministerial review, the airport was reported about 80 per cent complete with operations targeted for September to October 2026.
  3. 16 October 2026: the Chief Minister was told the airport is expected to be operational by the end of 2026, and that a calibration flight had recently landed.
  4. About 4 November 2026: the operation and management agreement was signed.

The airport is not open.

How the date has moved

The airport's date has been restated several times. DICDL's report for 2023-24 gave planned completion by 2026. An answer in Parliament in July 2025, as reported by DeshGujarat, gave December 2025. The ministry stated September to October 2026 in July 2026, and the end of 2026 was stated on 16 October 2026. The agreement does not change the end-of-2026 target. It is one of the steps that the target depends on.

What would show the airport is ready

Until one of these appears in an official or named source, the status stays: under construction, test landing complete, operating agreement signed, not open.

For anyone buying near the airport

A signed operating agreement is not an opening date, and a plot's value is not stated by any of these documents. Before relying on airport news for a purchase, confirm the plot's GujRERA registration, its title and the price for that exact plot.

Questions people ask

Has Dholera airport opened?

No. As of 11 November 2026 the airport is not open. The target is the end of 2026, as the Chief Minister was told on 16 October 2026. No aerodrome licence and no airline schedule has been reported.

What is the AAI DIACL agreement for Dholera airport?

It is an operation and management agreement between the Airports Authority of India and the Dholera International Airport Company Ltd, reported on 3 and 4 November 2026. No terms or opening date were published.

Who owns Dholera International Airport Company?

DIACL is a joint venture in which the Airports Authority of India holds 51 per cent, the Government of Gujarat 33 per cent and the National Industrial Corridor Development Corporation (NICDC) 16 per cent.

Which airlines will fly to Dholera?

No airline has announced a schedule as of 11 November 2026. Only non-official pages mention airlines in discussion, and we do not print those. An airline announcement or a published schedule would settle it.

Was there a test flight at Dholera airport?

Yes. An Airports Authority of India aircraft made the first trial landing on the 3,200 m runway on 4 June 2026, as reported by Gujarat Samachar. The Chief Minister's review on 16 October 2026 mentioned a calibration flight that had recently landed. Both were tests, not a passenger service.

Read next

Sources

  1. CAPA: AAI and DIACL sign O&M agreement for Ahmedabad Dholera airport (4 November 2026)
  2. Indian Masterminds: AAI and DIACL O&M agreement for Dholera greenfield airport (3 November 2026)
  3. NewKerala: Gujarat CM takes stock of projects in Dholera region, airport (16 October 2026)
  4. All India Radio: Dholera International Airport to become operational in three months (14 July 2026)