Top Dholera developers on the GujRERA register: what changed between August and November 2026

Updated 17 November 2026. Compiled by the Dholera SIR News desk from the sources listed at the end of this page.

Between our 4 August and 17 November 2026 reads, the GujRERA register for Dholera added no project: all 33 are the same. Sixteen declared completion dates changed, each by exactly four months, from Greenera Gardenvilla 2 (30 September 2026) to Shantiban Skylar (30 April 2030). Six complaint statuses changed. The register gives no reason for any change.

Check any developer here firstLook the company up on DholeraIntel's developer directory and read how to verify a Dholera developer before you pay. Then confirm the project's registration on the GujRERA portal and ask for the title papers of the exact plot. A place on this list records a public fact about a company. It is a starting point for your own checks.DholeraIntel is a sister publication of this site.
How this list is rankedThe list is ordered on one public fact: the declared completion date printed on each project's GujRERA page on 17 November 2026, earliest first. A project is listed only if that date differs from the one we recorded on 4 August 2026. Sixteen of the 33 registered Dholera projects qualify. The other 17 are left out because their date did not change. We do not report quarterly progress counts, because two of the changes in them look like register entry errors that we could not confirm.

The 16 projects whose declared completion date changed

No.ProjectPromoterGujRERA numberVillageDeclared completion, August readDeclared completion, 17 NovemberMonths moved
1Greenera Gardenvilla 2Greenera Infrawell Private LimitedPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA11450/EX1/010925/300526not stated in the record30 May 202630 September 20264
2GAP Industrial Park 1GAP Associates Private LimitedPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10173/EX1/030826/311226not stated in the record31 December 202630 April 20274
3Palm Greens Platinum 2Pacificus Superinfra LLPPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA09395/EX1/240326/311226not stated in the record31 December 202630 April 20274
4Dholera Megacity 771Dholera Mega City 771PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10217/200522not stated in the record31 December 202730 April 20284
5Dholera Megacity IrisInfinity Infracon (proprietorship)PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10133/020522not stated in the record31 December 202730 April 20284
6Park ViewInfinity Infracon (proprietorship)PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10465/180722not stated in the record31 December 202730 April 20284
7Bliss 107Satyaja InfratechPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12751/040124/310328Kadipur31 March 202831 July 20284
8Bliss Grandeur- 1Satyaja InfraconPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12734/030124/310328Kadipur31 March 202831 July 20284
9Bliss Grandeur- 2Satyaja InfraconPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12719/211223/310328Kadipur31 March 202831 July 20284
10Prelude Industrial ParkSatyaja InfratechPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12807/240124/310328Ambli31 March 202831 July 20284
11AakarGAP Studios LLPPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/RAA15713/190825/311228Bhimtalav31 December 202830 April 20294
12Shantiban DreamsParv Infracon LLPPR/GJ/AHMEDABAD/AHMEDABAD CITY/Dholera Special Investment Region Development Authority/MAA11736/A1M/281026/311228Dholera31 December 202830 April 20294
13Aaiji Residency 477Aaiji Infraspace (OPC) Private LimitedPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA15497/110725/311229Kadipur31 December 202930 April 20304
14ABCD Enclave IVSmarthomes Infrastructre Private LimitedPR/GJ/AHMEDABAD/DHANDHUKA/DSIRDA/PN70AA09970/080622Bhadiyad31 December 202930 April 20304
15Piccadilly Square IISmart Dholera Housing Private LimitedPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PN36AA09936/210522Kadipur31 December 202930 April 20304
16Shantiban SkylarSeksaria Buildcon LLPPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/MAA16212/151225/311229Dholera31 December 202930 April 20304

Ordered by the declared completion date on the 17 November 2026 read, earliest first. Sixteen of the 33 registered projects changed this one field; the other 17 show the same date as in August. Dates are as printed on the GujRERA project page. The register gives no reason for a change.

Download this table (CSV). Last checked 17 November 2026. Free to quote with a link to this page.

The 12 promoters behind the 16 changes

1. Greenera Infrawell Private Limited

  • Greenera Gardenvilla 230 May 2026 in August, 30 September 2026 on 17 November

One project of this promoter shows a different declared completion date on the 17 November read. The register moved it by four months. The new date had already passed on the day of the read, so the project page on the register is the place to see the stage the promoter reports. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

2. GAP Associates Private Limited

  • GAP Industrial Park 131 December 2026 in August, 30 April 2027 on 17 November

One project of this promoter shows a different declared completion date on the 17 November read. The register moved it by four months. The new date is still ahead of the day of the read. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

3. Pacificus Superinfra LLP

  • Palm Greens Platinum 231 December 2026 in August, 30 April 2027 on 17 November

One project of this promoter shows a different declared completion date on the 17 November read. The register moved it by four months. The new date is still ahead of the day of the read. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

4. Dholera Mega City 771

  • Dholera Megacity 77131 December 2027 in August, 30 April 2028 on 17 November

One project of this promoter shows a different declared completion date on the 17 November read. The register moved it by four months. The new date is still ahead of the day of the read. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

5. Infinity Infracon (proprietorship)

  • Dholera Megacity Iris31 December 2027 in August, 30 April 2028 on 17 November
  • Park View31 December 2027 in August, 30 April 2028 on 17 November

2 projects of this promoter show a different declared completion date on the 17 November read. Each moved by four months. The new date is still ahead of the day of the read. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

6. Satyaja Infracon

  • Bliss Grandeur- 131 March 2028 in August, 31 July 2028 on 17 November
  • Bliss Grandeur- 231 March 2028 in August, 31 July 2028 on 17 November

2 projects of this promoter show a different declared completion date on the 17 November read. Each moved by four months. The new date is still ahead of the day of the read. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

7. Satyaja Infratech

  • Bliss 10731 March 2028 in August, 31 July 2028 on 17 November
  • Prelude Industrial Park31 March 2028 in August, 31 July 2028 on 17 November

2 projects of this promoter show a different declared completion date on the 17 November read. Each moved by four months. The new date is still ahead of the day of the read. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

8. GAP Studios LLP

  • Aakar31 December 2028 in August, 30 April 2029 on 17 November

One project of this promoter shows a different declared completion date on the 17 November read. The register moved it by four months. The new date is still ahead of the day of the read. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

9. Parv Infracon LLP

  • Shantiban Dreams31 December 2028 in August, 30 April 2029 on 17 November

One project of this promoter shows a different declared completion date on the 17 November read. The register moved it by four months. The new date is still ahead of the day of the read. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

10. Aaiji Infraspace (OPC) Private Limited

  • Aaiji Residency 47731 December 2029 in August, 30 April 2030 on 17 November

One project of this promoter shows a different declared completion date on the 17 November read. The register moved it by four months. The new date is still ahead of the day of the read. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

11. Seksaria Buildcon LLP

  • Shantiban Skylar31 December 2029 in August, 30 April 2030 on 17 November

One project of this promoter shows a different declared completion date on the 17 November read. The register moved it by four months. The new date is still ahead of the day of the read. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

12. Smart Dholera Housing Private Limited

  • Piccadilly Square II31 December 2029 in August, 30 April 2030 on 17 November

One project of this promoter shows a different declared completion date on the 17 November read. The register moved it by four months. The new date is still ahead of the day of the read. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

13. Smarthomes Infrastructre Private Limited

  • ABCD Enclave IV31 December 2029 in August, 30 April 2030 on 17 November

One project of this promoter shows a different declared completion date on the 17 November read. The register moved it by four months. The new date is still ahead of the day of the read. The register does not state a reason. For a buyer of one of these plots, the date to hold is the one printed in the agreement for sale, and it is worth comparing it with the register date.

Who this list is for

This page is for anyone who read a Dholera project's completion date in August and wants to know whether the register still shows the same date. It is also for a buyer who holds an agreement for sale from one of these promoters and wants to compare the date in the agreement with the date on the public register. Read it as a change log for Dholera builders: the 33 projects and their promoters are the same as in August.

The page does not rank promoters by quality. It records which entries on the register changed, and by how much, between two dated readings of the same public source. That is the part a news desk can state without opinion.

What the register shows, and what it does not

GujRERA is the Gujarat Real Estate Regulatory Authority. A promoter registers a project and states a completion date, and the authority publishes it. The page for each project also lists quarterly progress filings and any complaints made to the authority.

On 17 November 2026 the register held the same 33 Dholera projects as on 4 August 2026. During the same period the Ahmedabad district list grew from 5,435 to 5,538 projects, and none of the 103 additions was a Dholera project. In plain terms, the registered stock in Dholera did not grow in three and a half months, but the dates inside it moved.

Every one of the 16 changes is exactly four months later than the August date. The register does not state why. A promoter can apply to extend a registration, and several Dholera registrations already carry an extension marker in their number, but the project page does not say which request produced a given new date. We therefore report the old date and the new date and nothing else.

How to read a changed date

A declared completion date is the date the promoter gave the authority for finishing the project. It is not a delivery guarantee and not an inspection result. Three readings are possible from the table alone.

After the changes, 17 of the 33 projects show a declared completion date earlier than 17 November 2026. That count is computed from the register fields. It does not say how many are finished, because the register records the declared date and a quarterly filing history, not a completion certificate in the summary view.

Complaint statuses that moved

Six complaint statuses changed between the two reads. A complaint on the register is a filing made by a buyer or another party. It is not a finding against the promoter. The statuses below are the words the register uses.

Across all 33 projects the register lists 16 complaints on 13 projects: 9 with HEARING_SCHEDULE, 6 CLOSED and 1 BENCH_ASSIGN on 17 November. The other 20 projects list none.

How to check any of this yourself in five minutes

  1. Open the GujRERA site at gujrera.gujarat.gov.in.
  2. Use the project search and enter the project name or the registration number printed in the table above.
  3. Open the project page and find the line for the proposed date of completion. Compare it with the August and November columns here.
  4. On the same page open the quarterly progress section and the complaints section. The status words appear exactly as quoted on this page.
  5. Ask the promoter for the date written in your agreement for sale and compare the two. A difference is worth a written question, not an assumption.

The register pages are an application that loads its data, so a printed copy of the page is the safest record of what you saw and when.

What stayed the same

Seventeen projects show the same declared completion date on both reads, including the Fidato Luxuria projects, the Nest 29 project and the older 7 Oak projects. Among the fields we compare, one land-area field also changed: the project area printed for Shantiban Dreams in August is blank on 17 November, a field the register itself leaves empty on several DSIRDA-era entries.

What this list cannot tell you

This list compares two readings of one public register, three and a half months apart. It cannot tell you why a date moved, whether a project has been completed, what is happening on a plot, or whether the date in your own agreement matches the register. It does not cover promoters outside the GujRERA Dholera filter. Single-person firms are shown by firm name, and no contact detail is printed. A number or date shown only inside an image or a PDF on the register would not be seen by this check.

Questions people ask

Did any new Dholera project register on GujRERA between August and November 2026?

No. The register held the same 33 Dholera projects on 17 November 2026 as on 4 August 2026. The Ahmedabad district list grew from 5,435 to 5,538 projects over the same period, but none of the additions carried Dholera evidence in its registration number, authority or village.

Why did 16 Dholera completion dates change on the GujRERA register?

The register does not state a reason on the project page. Each new date is exactly four months after the August date. Registrations can carry an extension, and the extension markers visible in some registration numbers show that extensions exist, but this page cannot say which request produced which date.

Does a changed completion date mean a Dholera project is delayed?

The register shows only the old and new declared dates, so this page does not label any project. A declared date is the promoter's statement to the authority. What a buyer can do is compare it with the date in the agreement for sale and ask the promoter in writing.

How many Dholera projects now show a completion date that has already passed?

Seventeen of the 33 registered projects show a declared completion date before 17 November 2026, after the 16 changes. The register does not summarise completion certificates, so this count is not a count of unfinished projects.

What do HEARING_SCHEDULE and BENCH_ASSIGN mean on a GujRERA complaint?

They are status words shown by the register. HEARING_SCHEDULE indicates a hearing has been scheduled and BENCH_ASSIGN indicates a bench has been assigned. They describe where a filing sits in the authority's process. Neither is a decision on the complaint.

Where can I see the same changes on the official register?

Open the GujRERA site, search for the project by name or registration number, and read the proposed completion date, the quarterly progress section and the complaints section. The registration numbers in the table above are copied from the register.

Read next

Sources

  1. GujRERA project register, Ahmedabad district list, Dholera filter, re-read (read 17 November 2026)
  2. GujRERA project register, same filter, first read (read 4 August 2026)
  3. GujRERA public project page (project details, quarterly progress and complaints sections), for example project 26738 (17 November 2026)
  4. Real Estate (Regulation and Development) Act 2016, section 6, extension of registration (Act as in force, checked 17 November 2026)