How much land has been allotted in Dholera: 14 plots and 545 acres in the latest official report
Updated 11 November 2026. Compiled by the Dholera SIR News desk from the sources listed at the end of this page.
The National Industrial Corridor Development Corporation's delivery-monitoring report dated 30 September 2026 says 14 plots measuring 545 acres have been allotted in Dholera, 476 acres of them industrial with Tata Chemicals as the anchor investor. It also lists 1,043 acres of industrial land and 1,031 acres of other uses as available. The totals match 30 June 2026.
Land allotted in Dholera, by official report date
| Report date | Plots allotted | Acre allotted, all uses | Of which industrial acre | Industrial acre available | Other-use acre available | Change from the previous edition held |
|---|---|---|---|---|---|---|
| 30 September 2026 | 14 | 545 | 476 | 1,043 | 1,031 | No change |
| 30 June 2026 | 14 | 545 | 476 | 1,043 | 1,031 | +2 plots, +41 acre |
| 31 May 2026 | 12 | 504 | 436 | 1,083 | 1,032 | No new plot, +1 acre |
| 31 January 2026 | 12 | 503 | 436 | 1,083 | 1,033 | No change |
| 30 November 2025 | 12 | 503 | 436 | 1,083 | 1,033 | +1 plot, +8 acre |
| 31 October 2025 | 11 | 495 | 428 | 1,091 | 1,033 | No change |
| 30 September 2025 | 11 | 495 | 428 | 1,091 | 1,033 | No change |
| 31 August 2025 | 11 | 495 | 428 | 1,091 | 1,033 | No change |
| 30 June 2025 | 11 | 495 | 428 | 1,091 | 1,033 | First edition held |
9 NICDC delivery-monitoring reports are shown, newest first; 0 were dropped for missing values. Months not shown (July, December, February to April, July and August) are reports we do not hold, and nothing is interpolated. Allotted area covers all land uses and is cumulative. Source: NICDC proforma for the Delivery Monitoring Unit, DPIIT, section 1.1 of each edition.
Download this table (CSV). Last checked 11 November 2026. Free to quote with a link to this page.
Newest edition first; the figure moved only in November 2025, May 2026 and June 2026.
What the latest report says
NICDC files a monthly proforma with the Delivery Monitoring Unit of the Department for Promotion of Industry and Internal Trade. Its Dholera paragraph states the planned area of about 920 sq km, the 22.5 sq km activation area where trunk infrastructure is described as complete, and the allotment totals. The edition dated 30 September 2026, which we read on 13 November 2026, gives 14 plots of 545 acres allotted, of which 476 acres are industrial, with Tata Chemicals named as the anchor investor. It lists 1,043 acres of industrial land and 1,031 acres of commercial, residential and other land as readily available.
What moved, and when
The count sat at 11 plots and 495 acres from the first edition we hold, dated 30 June 2025, through 31 October 2025. A twelfth plot appeared in the 30 November 2025 edition, adding 8 acres, all of them industrial. A single acre was added in the 31 May 2026 edition without a new plot. The largest step came in the 30 June 2026 edition: two more plots and 41 acres, 40 of them industrial, taking the totals to 14 and 545. The 30 September 2026 edition repeats those figures. Our wire entries on the twelfth plot and the June 2026 report cover two of the steps.
How much land is still available
The same nine editions show the industrial land still available shrinking from 1,091 acres in June 2025 to 1,083 acres in November 2025, then to 1,043 acres in June 2026, where the 30 September 2026 edition leaves it. Land available for other uses moved far less, from 1,033 acres to 1,031 acres. Allotted industrial land is 476 acres in the latest edition against 428 acres in June 2025. These are NICDC's own totals for allotment, not for sales, construction or occupation, so they say nothing about how much of the allotted land is in use.
Who received the land
The reports give a count, an area and an anchor investor, and nothing else. They name no allottee besides Tata Chemicals as the anchor, give no plot numbers, no allotment dates and no rates. DICDL's own annual report for 2024-25 names four industrial allottees and states that the list is not exhaustive: Tata Semiconductor Manufacturing, ReNew Photovoltaics, Polycab India and INOX Air Products. It attaches no acreage to any of them. So the question who got the extra 41 acres in the June 2026 edition cannot be answered from the record.
Two official counts that do not match
DICDL's annual report states 530 acres of industrial land allotted cumulatively at 31 March 2025, with 1,519 acres available. The NICDC report dated 30 June 2025 states 495 acres allotted across all uses, 428 of them industrial, and 1,091 acres of industrial land available. The two industrial figures sit three months apart and differ by more than 100 acres. The available figure of 1,519 acres equals 428 plus 1,091, which suggests the annual report counts the industrial land before the allotments. That is a reading and not a source, so we print both and leave them unreconciled.
What the totals do not mean
Allotted land is not built land, and an allotment is not a purchase price paid in full. The reports say nothing about how much of the 545 acres has a building on it, how much has been paid for, or how much is the Tata semiconductor site. The available acres are land the report calls readily available, not land priced or advertised. Anything beyond those counts needs a DICDL document. The land transfer rules and fees are covered in the DICDL allotment policy summaries on sister sites, and the NICDC monitoring reports source page explains how we read these reports.
Why the 30 September edition matters even with no change
A report that repeats a figure is evidence too. Between 30 June and 30 September 2026 the monitoring paragraph for Dholera added no plot and no acre, and it kept the 300 MW solar figure and the airport wording of construction works underway. Dholera's airport carries a target for the end of 2026 in the Chief Minister's 16 October 2026 review, and a monitoring report that still says works are underway is consistent with that. It does not confirm it.
How to check the next edition
The report is a PDF on the NICDC site at a stable address that is overwritten each month, so an old copy is not the current one. Read section 1.1, look for the sentence beginning with the number of plots, compare it with the table above and note the date printed in the header. The Bhavnagar expressway page and the rail status page show the same habit of dating each claim.
What this page cannot tell you
This page reports counts from NICDC's monthly reports for nine dates. It cannot tell you who holds the land, what was paid, what has been built, or the market value of any plot.
Questions people ask
How much land has been allotted in Dholera?
NICDC's report dated 30 September 2026 says 14 plots measuring 545 acres have been allotted, including 476 acres of industrial land with Tata Chemicals as the anchor investor. The same totals appear in the report dated 30 June 2026.
How much land is available for allotment in Dholera?
The 30 September 2026 report lists 1,043 acres of industrial land and 1,031 acres of commercial, residential and other land as readily available. DICDL's 2024-25 annual report separately states 1,519 acres of industrial land available.
Who has been allotted land in Dholera?
NICDC names Tata Chemicals as the anchor investor. DICDL's 2024-25 annual report lists Tata Semiconductor Manufacturing, ReNew Photovoltaics, Polycab India and INOX Air Products as named industrial allottees, a list it says is not exhaustive, with no acreage.
Has Dholera land allotment increased in 2026?
Yes. The count went from 12 plots and 503 acres in January 2026 to 14 plots and 545 acres in the report dated 30 June 2026, an increase of 41 acres from May. It was unchanged in the 30 September 2026 edition.
What is the DICDL land price for allotment?
DICDL's land pricing policy lists government rates per square metre by land use. The monitoring reports give no price per plot or per acre. The policy table is summarised on our sister property site.
Is the Dholera land allotted already built on?
The reports do not say. They count allotments and acres, not construction. Construction at the Tata fab and other sites is covered separately in the wire and has no percentage in these reports.
Read next
- The NICDC report of June 2026
- The twelfth plot allotted
- NICDC monitoring reports
- Dholera Bhavnagar expressway status
- Dholera metro rail: no metro approved, a 134 km rail line is
Sources
- NICDC proforma for the Delivery Monitoring Unit, DPIIT: status of industrial corridor projects, section 1.1 Dholera (edition dated 30.09.2026) (30 September 2026, read 13 November 2026)
- DPIIT: Status of industrial corridor projects, NICDC editions 2025 and 2026 (editions dated 30 June 2025 to 30 June 2026)
- DICDL 9th Annual Report 2024-25, land allotted and named industrial allottees (signed 22 August 2025)