The dated, sourced record of the Dholera Special Investment Region in Gujarat. Every entry carries the date it happened, the source it came from, and a plain label telling you how solid it is. Nothing on this site is for sale.
Last reviewed 11 August 2026

Is the Tata fab in Dholera on track? What the reports show in November 2026

Updated 11 November 2026. Compiled by the Dholera SIR News desk from the sources listed at the end of this page.

The Cabinet approved the Tata Electronics and PSMC fab at Dholera on 29 February 2024, and production is guided for mid-2028. Reports from July to November 2026 describe construction under review, gas piping started and supplier deals signed. No official percent complete has been published, so a claim that the fab is a set percent built cannot be checked as of 13 November 2026.

Fab reports, July to November 2026, newest first

DateWhat was reportedSourceLabel
6 November 2026INOX India begins initial piping work at the Dholera fab; management says the first phase may need 500 to 600 km of pipingMultibagg, results call coverageReported
16 to 17 October 2026Chief Minister reviews construction of the fab; no completion figure given in the reportNewKerala wireReported
12 October 2026Tata is reported to have six customers at different stages, three reportedly with binding offtake commitmentsDigitimes, anonymous sourceReported, single trade source, unconfirmed
4 October 2026A 363-acre vendor park near the fab is reported in developmentChannelIAMReported
17 September 2026Fujifilm and Tata Electronics sign an MoU; Fujifilm plans about Rs 800 crore in phases for a materials plant in Dholera SIRFujifilm press releaseCompany statement, a plan not a built plant
20 July 2026Bloomberg, via TrendForce, reports the fab will launch mostly on 90nm; Tata says the range will span 28nm to 110nmTrendForceReported, node mix not confirmed by Tata

Download this table (CSV). Last checked 11 November 2026. Free to quote with a link to this page.

What is officially fixed

The Union Cabinet approved the fab on 29 February 2024 for up to 50,000 wafers a month. The date is recorded in this site's wire entry on the approval. Production has been guided for mid-2028, a date the electronics minister has also given. It is a target, not a delivered result.

What construction reports say

The fullest 2026 report is the 16 October 2026 state review, which says construction was reviewed. It does not give a percent complete. The 6 November report says INOX India had begun initial piping work, which is one scope of many inside a fab. Piping starting means that part of the build has begun. It does not show how much of the fab is finished.

Two claims this site does not repeat

Some pages say the fab is around 50 percent complete. An April 2026 page gave the same figure, so the number has not changed across months, which suggests it is not a current reading. Some pages also say production starts in December 2026. That conflicts with the mid-2028 guidance. Neither claim has an official source, so neither is printed here.

Customers and suppliers

The Digitimes report of six customers rests on an anonymous source and has not been confirmed by Tata. The supplier side is firmer: Tata Electronics signed 16 MoUs at SEMICON India in September 2026, and the CEO described them as operational commitments, not immediate revenue. An MoU is an agreement to cooperate. It does not say a plant has been built.

Why the node report matters

A 28nm chip and a 90nm chip serve different markets. The July report says early output is mostly 90nm. Tata's own statement describes a range from 28nm to 110nm. Both can be true if 28nm comes later. The record does not say when.

How to track it yourself

Watch for Tata Electronics or PSMC releases, Ministry of Electronics and IT statements, and the NICDC monthly progress reports on the Dholera trunk infrastructure that serves the fab. A measured figure from any of those is worth more than a broker or portal percentage. Verify GujRERA registration, title and price for any plot near the fab, whatever the fab news says.

A line only this site can say

This site's wire carries the fab's approval, the SEZ notification, the Tata fiscal support agreement and the lithography partnership as separate dated entries, so each step can be read in order.

What this page cannot tell you

This page lists reports. It cannot measure construction progress or confirm a customer, a node or a production date.

Questions people ask

Is the Tata semiconductor fab in Dholera under construction?

Yes, according to reports. The Chief Minister reviewed its construction on 16 October 2026, and INOX India began piping work reported on 6 November 2026. No official percent complete has been published.

When will the Dholera fab start production?

Production is guided for mid-2028, a date also given by the electronics minister. It is a target. A claim of production in December 2026 conflicts with that guidance and has no official source.

How much of the Tata Dholera fab is complete?

Not stated in the record. Pages that say about 50 percent give no official source, and the same figure appeared in April 2026. This page does not print a percent.

What technology will the Dholera fab use?

Tata says its fab will span 28nm to 110nm. Bloomberg, via TrendForce on 20 July 2026, reported it will launch mostly on 90nm. Tata has not confirmed the mix for launch.

Who are the customers of the Tata Dholera fab?

No customer has been named by Tata in the record. Digitimes reported on 12 October 2026, from an anonymous source, six customers at different stages. Treat it as unconfirmed.

Has Fujifilm built a plant in Dholera?

No. Fujifilm announced on 17 September 2026 a plan of about Rs 800 crore in phases for a semiconductor materials plant in Dholera SIR. It is an MoU and a plan, not a built plant.

Read next

Sources

  1. INOX India Dholera semiconductor piping, Multibagg market pulse (6 November 2026)
  2. Gujarat CM takes stock of projects in Dholera region, NewKerala (16 October 2026)
  3. Digitimes report on Tata customers (12 October 2026)
  4. Tata Electronics Dholera vendor park, ChannelIAM (4 October 2026)
  5. Fujifilm and Tata Electronics strategic partnership, Fujifilm India (17 September 2026)
  6. Tata's India fab reportedly to launch at 90nm, TrendForce (20 July 2026)